Recommendations for the arrangement of internal pipeline systems for water supply, sewerage and fire safety, including the use of polymer pipes. Engineering networks of buildings and structures are internal. Recommendations for the installation of internal pipes
1 area of use
2 Normative references
3 Terms and definitions, designations and abbreviations
4 General provisions
5 Pressure pipes
5.1 Requirements for pressure tubing
5.2 Pressure pipes
5.2.1 Pressure steel pipes
5.2.1.1 Connecting parts for steel pipes
5.2.1.2 Connections for steel pipes
5.2.2 Pressure copper pipes
5.2.2.1 Connections for copper pipes
5.2.2.2 Connections for copper pipes
5.2.3 Metal-polymer pressure pipes
5.2.3.1 Metal fittings polymer pipes
5.2.3.2 Joints for multilayer pipes
5.2.4 Polypropylene pressure pipes
5.2.4.1 Fittings for polypropylene pipes
5.2.4.2 Connections for polypropylene pipes
5.2.5 XLPE pressure pipes
5.2.5.1 Fittings for XLPE pipes
5.2.5.2 Connections for XLPE pipes
5.2.6 Chlorinated PVC pressure pipes
5.2.6.1 Connections for chlorinated PVC pipes
5.2.6.2 Chlorinated PVC pipe fittings
5.2.7 Polybutene pressure pipes
5.2.7.1 Fittings for polybutene pipes
5.2.7.2 Connections for polybutene pipes
5.2.8 Acrylonitrile butadiene styrene pressure pipes
5.2.8.1 Fittings for acrylonitrile butadiene styrene pipes
5.2.8.2 Connections for acrylonitrile butadiene styrene pipes
5.3 Technological features of the connection of pressure polymer pipes
5.3.1 Types of connections for pressure plastic pipes
5.3.2 Welding of polyolefin pressure tubing
5.3.3 Pressure tubing connections made of unplasticized PVC, chlorinated PVC and acrylonitrile butadiene styrene
5.3.4 Welding of polypropylene pressure tubing
5.4 Fastening pressure pipes
6 Sewer pipes
6.1 Requirements for sewer pipes
6.2 Sewer pipes
6.2.1 Gray cast iron sewer pipes
6.2.1.1 Connecting parts for sewer pipes gray cast iron
6.2.1.2 Gray cast iron sewer pipe connections
6.2.2 Ductile iron sewer pipes
6.2.2.1 Ductile iron sewer fittings
6.2.2.2 Ductile iron sewer pipe connections
6.2.3 Unplasticized PVC sewer pipes
6.2.3.1 Connections for unplasticized PVC sewer pipes
6.2.3.2 Connections for unplasticized PVC sewer pipes
6.2.4 Thick-walled PVC sewer pipes
6.2.4.1 Connections for heavy-wall PVC sewer pipes
6.2.4.2 Connections for heavy-wall PVC sewer pipes
6.2.5 Sewer pipes made of polyethylene
6.2.5.1 Connections for polyethylene sewer pipes
6.2.5.2 Connections for polyethylene sewer pipes
6.2.6 Sewer pipes made of filled polyethylene
6.2.6.1 Connections for sewer pipes made of filled polyethylene
6.2.6.2 Connections for sewer pipes made of filled polyethylene
6.2.7 Polypropylene sewer pipes
6.2.7.1 Connection parts for polypropylene sewer pipes
6.2.7.2 Connections for socket sewer pipes made of polypropylene
6.2.8 Sewer pipes made of filled polypropylene
6.2.8.1 Connections for sewer pipes made of filled polypropylene
6.2.8.2 Connections for sewer pipes made of filled polypropylene
6.2.9 Connections for assembling different sewer pipes
6.3 Fasteners for gravity pipelines
7 Pipe procurement
7.1 Bending pipes for pressure and sewer pipes
7.2 Manufacture of blanks from pressure pipes for water pipes
7.3 Manufacture of pressure pipes polyethylene pipes for water pipes
7.4 Manufacture of blanks for internal fire water pipelines
7.5 Manufacture of water seals for internal drains
7.6 Manufacture of units from polymer sewer pipes
7.7 Completion of shaft packages with pressure water and sewer pipe blanks
7.8 Acquisition of sanitary cabins with pressure water and sewer pipe blanks
7.9 Making bays-risers for internal drains
8 Installation of internal water pipes
8.1 Typical structures technological processes installation of internal water pipes
8.2 Technical documentation for installation and assembly work
8.3 Organization of work on the installation of internal water pipes
8.4 Preparatory work
8.5 Auxiliary work
8.6 Assembly of internal plumbing
9 Installation of sewer pipelines
9.1 Typical installation process structures internal sewerage
9.2 Requirements for the project of internal sewerage
9.3 Requirements for the installation project of internal sewerage
9.4 Assembling the internal sewer system
9.5 Quality control of the assembly of sewer pipelines
10 Installation of internal drains
10.1 Arrangement of internal drainage systems
10.2 Typical structures of technological processes for the installation of internal gutters
10.3 Production installation work for the assembly of internal gutters
10.4 Quality control of the assembly of internal gutters
11 Testing of internal piping systems
11.1 Testing cold and hot water pipes
11.2 Testing fire-fighting water pipes
11.3 Testing sewer pipes
11.4 Testing of internal drains
12 Handover and acceptance of internal pipelines
12.1 General
12.2 Delivery and acceptance of internal water pipes
12.3 Delivery and acceptance of internal sewerage
12.4 Delivery and acceptance of internal drains
13 Safety, Fire safety and environmental safety in the construction of internal pipeline systems
Annex A (informative). Symbols of sewer pipe products
Appendix B (recommended). The form of the certificate of examination of hidden works on internal systems water supply and sanitation
Annex B (recommended). The form of the act based on the results of tests of cold / hot water supply
Appendix D (recommended). The form of the act based on the results of tests of the internal sewerage system
Annex D (recommended). The form of the act based on the results of tests of the internal drainage system
Annex E (recommended). A sample of the act of testing the internal fire-fighting water supply for performance
Appendix G (recommended). Sample test report for internal fire water supply for water loss
Annex I (recommended). Sample test report for fire hydrants for serviceability
Annex K (recommended). Sample certificate of acceptance of internal fire-fighting and utility and hot water pipes
Annex L (recommended). Sample act of acceptance of internal sewerage
Annex M (recommended). Sample act of acceptance of internal drains
Bibliography
NATIONAL ASSOCIATION OF BUILDERS Organization Standard
Rules, performance control, requirements for the results of work
STO NOSTROY 2.15.177-2015
EDITION OFFICIAL
NATIONAL ASSOCIATION OF BUILDERS
Organization Standard
Network engineering buildings and structures internal
DEVICE OF VENTILATION AND AIR-CONDITIONING SYSTEMS OF SERVER ROOMS
Rules, performance control, requirements for the results of work
STO NOSTROY 2.15.177-2015
Official edition
Closed joint-stock company"ISZS - Consult" Limited Liability Company "BST" Publishing House
STO BUILD 2.15.129-2013 Engineering networks of buildings and structures are internal. Electrical installations of buildings and structures. Production of electrical work. Part 1. General requirements
STO NOS "GROY / NOP 2.15.163-2014 Internal engineering networks of buildings and structures. Air conditioning systems with variable refrigerant flow. Design and installation rules, implementation control, requirements for the results of work
STO NOSTROY 2.15.178-2015 Internal engineering networks of buildings and structures. precision air conditioners. Installation and commissioning. Rules, performance control, requirements for the results of work
STO NOSTROY 2.23.1-2011 Internal engineering networks of buildings and structures. Installation and commissioning of evaporative and compressor-condenser units of domestic air conditioning systems in buildings and structures. General technical requirements
STO NOSTROY 2.23.85-2013 Technological equipment and technological pipelines of ferrous metallurgy enterprises. General requirements for the production of installation, commissioning and acceptance of work
STO NOSTROY 2.23.164-2014 Internal engineering networks of buildings and structures. The device of the refrigeration centers. Rules, performance control, requirements for the results of work
STO NOSTROY 2.24.2-2011 Internal engineering networks of buildings and structures. Ventilation and air conditioning. Testing and adjustment of ventilation and air conditioning systems
R NOSTROY 2.15.3-2011 Internal engineering networks of buildings and structures. Recommendations for testing and adjustment of ventilation and air conditioning systems
Note - When using this standard, it is advisable to check the effect of reference regulatory documents in the public information system - on the official websites of the national authority Russian Federation on standardization and on the web
STO POSTROY 2.15.177-2015
Internet or according to annually published information indexes published as of January 1 of the current year If reference document replaced (modified, updated), then when using this standard, one should be guided by a new (modified, updated) document.
3 Terms and definitions
This standard uses terms in accordance with GOST 22270-76, GOST R 52720-2007, SP 60.13330.2012, as well as the following terms with the corresponding definitions:
3.1 ventilation: The exchange of air in rooms in order to remove excess heat, moisture, harmful and other substances in order to ensure an acceptable microclimate and air quality in a serviced or working area(according to SP 60.13330.2012, paragraph 3.2).
3.2 indoor unit (air conditioning indoor unit):
Part of the air conditioning system installed inside the serviced premises and ensuring the maintenance of the specified microclimate parameters in it.
3.3 air exchange: The process of replacing indoor air in a room by natural ventilation or ventilation equipment.
Note - Quantitatively, air exchange is determined by the volume of air supplied to the room or removed from it, per unit of time (usually in m '/h), as well as the ratio of the volume of air supplied or removed for 1 hour to the volume of the room (air exchange rate)
(According to STO NOSTROY 2.24.2-2011, paragraph 3)).
3.4 hot aisle: The corridor, which is formed, as a rule, by the back sides of cabinets and racks with server and telecommunications equipment.
Note - The hot aisle is characterized by a higher air temperature, since air heated by server and telecommunications equipment enters the hot aisle, which is then supplied to the air conditioners for cooling
3.5 duct air conditioner (duct air conditioner): An air conditioner intended for concealed mounting by hanging from the ceiling and providing for the connection of external devices for air intake and distribution.
3.6 air conditioning: automatic maintenance of all or individual air parameters (temperature, relative humidity, cleanliness and mobility) in the serviced premises in order to ensure the specified microclimate parameters, as a rule, optimal meteorological conditions that are most favorable for people's well-being, the conduct of the technological process, and ensuring safety values.
3.7 outdoor unit (outdoor unit of the air conditioning system): Part of the air conditioning system, installed outside the serviced premises and designed to transfer heat from the refrigerant to environment or other coolant.
3.8 microclimate: The state of the internal environment of the room, characterized by the following indicators: air temperature, radiation temperature, relative humidity, air exchange, air velocity, gas composition, acoustic spectrum, content of solid particles and microorganisms in the air in the room (according to STO NP "ABOK" 2.1 -2008 ).
3.9 ceiling-mounted air conditioner (ceiling-mounted air conditioner): an air conditioner designed for open mounting by hanging from the ceiling and having standard devices for air intake and distribution in its design.
STO NOSE TRON 2.15.177-2015
precision air conditioner: Local air conditioner designed for
maintenance of premises in which it is necessary to maintain the temperature and (or) relative humidity of the air with a given accuracy.
Note - May be of the following design
Autonomous - including a refrigeration circuit;
Non-autonomous - with a water air cooler connected to an air-cooled machine.
[STO BUILD 2.15.178-2015, paragraph 3.4]
3.11 Precision cabinet air conditioner: Precision air conditioner for installation on the floor.
3.12 working environment: Liquid, gas, slurry or mixtures thereof, for the control of which the valve is intended, or used to control the valve, or surrounding it (according to GOST R 52720-2007, article 2.16).
3.13 server hardware: Hardware designed to run service software on it.
Note - The server equipment includes the RA apparatus and electronic computing equipment with software
3.14 server room: A technological room occupied by server and (or) telecommunications equipment with specially created and maintained microclimate parameters.
3.15 ventilation system (ventilation equipment): A set of engineering devices that provide controlled air exchange in the room in order to maintain the specified air parameters.
3.16 ventilating system: a ventilation system designed to remove air from a room.
3.17 supply ventilation system: A ventilation system designed for preparation (depending on requirements - heating, cooling, humidification, cleaning, etc.) and air supply to the premises.
3.18 gas removal system: A set of equipment designed to remove exhaust air with carbon dioxide and harmful fumes, as well as gases and smoke after a fire.
3.19 air conditioning system A set of engineering devices that provide specified microclimate parameters and (or) controlled air exchange in the room
3.20 dust removal system: A set of equipment designed to clean indoor air from dust and other solid particles.
3.21 condensate removal system: A set of equipment designed to remove condensate that forms on the surface of the equipment from the place of its accumulation to the place of discharge (for example, into the sewerage system of the building).
rack: metal structure without doors or trim.
(According to GOST 28601.2-90, article 2)
4 Notation and abbreviations
11D - design documentation; NDP - project for the production of works; RD - working documentation;
TK - terms of reference;
HVS - cold water supply.
5 General requirements 5.1 Requirements for service rooms
5.1.1 Server rooms must be equipped with a mechanically driven ventilation system and an air conditioning system, and, if necessary, a dust removal system.
Notes
1 In server rooms it is allowed not to provide a ventilation system if they:
There are no permanent jobs;
There are no batteries or equipment that requires a ventilation system to operate.
2 In server rooms equipped with gas or powder fire extinguishing, gas exhaust systems should be installed in accordance with subsection 6 4.
Distribution / application of this standard is carried out in accordance with the current eaconodate. i not yours and in accordance with the rules established by the National Association of Builders
STO BUILD 2.15.177-2015
1 area of use............................................... ................................................. ...one
3 Terms and definitions .......................................................... ................................................5
4 Symbols and abbreviations.................................................... ..........................................9
5 General requirements ............................................... ................................................. .....9
5.1 Requirements for service rooms............................................................... ..................9
5.2 Requirements for related engineering systems that provide
impact on ventilation and air conditioning .............................................................. ........ten
6 Design of ventilation systems .......................................................... .................................II
6.1 Design parameters for ventilation systems............................................................... ....eleven
6.2 Organization of air exchange of ventilation systems ..............................................11
6.3 Requirements for elements of supply ventilation systems .............................................. 12
6.4 Requirements for the degassing system in server rooms .........................................13
6.5 Installation of ventilation systems for server rooms...............................................13
7 Installation of air conditioning systems .................................................... ...................fourteen
7.1 Design parameters for air conditioning systems...............................................................14
7.2 Organization of air exchange of air conditioning systems...............................................15
7.3 Requirements for the air-conditioning system of server rooms...............................18
7.4 Ensuring the reliability of air conditioning systems in server rooms
premises ................................................. ................................................. ........twenty
7.5 Installation of the outdoor unit of air conditioning systems
server rooms ................................................................ .........................................21
7.6 Mounting indoor unit air conditioning systems
server rooms ................................................................ ................................................22
7.7 Mounting considerations for precision cabinet air conditioners
STO POSTROY 2.15.177-2015
7.8 Features of installation of duct and ceiling air conditioners
in server rooms ........................................................ ....................................23
7.9 Installation of piping for server room air conditioning systems
premises ................................................. ................................................. .........24
7.10 Installation of pipelines for the condensate removal system in server rooms
7.11 Installation of the power supply and control system in server rooms
premises ................................................. ................................................. .....26
7.12 Complex adjustment ventilation and air conditioning systems
server room ................................................................ ......................................27
8 Work progress control .................................................................. ...............................................28
Annex A (mandatory) Technological operations, subject to
control during installation work .............................................33
Annex B (mandatory) Compliance card form
requirements of STO NOSTROY 2.15.177-2015 .....................................44
Bibliography................................................. ................................................. .............52
STO BUILD 2.15.177-2015
Introduction
This standard was developed within the framework of the Standardization Program of the National Association of Builders and is aimed at implementing the Town Planning Code of the Russian Federation, federal law dated December 27, 2002 No. 184-FZ "On technical regulation". Federal Law of December 30, 2009 No. 384-FZ "Technical Regulations on the Safety of Buildings and Structures".
This standard specifies the requirements of SP 60.13330.2012 (section 7) and SP 73.13330.2016 (subsections 6.5, 7.5, 7.6, 8.3) regarding ventilation and air conditioning systems of server rooms.
The standard sets out the basic requirements and rules for performing work on the installation of ventilation and air conditioning systems for server rooms, taking into account the specifics of this type of objects: the need to ensure increased reliability in the operation of ventilation and air conditioning systems, increased heat inflows, equipment placement, air exchange, etc.
With the participation of: S.V. Mironova, V.I. Tokarev (Soyuz "ISZS-Montazh").
STO NOSTROY 2.15.177-2015
STANDARD OF THE NATIONAL ASSOCIATION OF BUILDERS
Engineering networks of buildings and structures internal DEVICE OF VENTILATION SYSTEMS II FOR AIR CONDITIONING OF SERVER ROOMS Rules, control of implementation, requirements for * results of work
Internal buildings and structures utilities Constructing of ventilation and conditioning systems of server rooms Rules, monitoring control, requirements to the results of works
1 area of use
1.1 This standard applies to ventilation and air conditioning systems used to ensure microclimate parameters in server rooms and establishes requirements, rules and control of work. The provisions of section 5, subsections 6.1 - 6.4, 7.1 - 7.4 are recommended.
1.2 Liquid cooling systems for server and telecommunications equipment, as well as free cooling systems for server rooms, are not subject to this standard.
2 Normative references
This standard uses normative references to the following standards and codes of practice:
GOST 8.398-80 State system ensuring the uniformity of measurements. Instruments for measuring the hardness of metals and alloys. Methods and means of verification
And manne official
GOST 12.3.018-79 System of labor safety standards. Ventilation systems. Aerodynamic test methods
GOST 166-89 Calipers. Specifications GOST 427-75 Measuring metal rulers. Specifications GOST 1508-78 Control cables with rubber and plastic insulation. Specifications Instruments for measuring electrical and magnetic quantities. General specifications
SP 48.13330.2011 "SNiP 12-01-2004 Organization of construction"
SP 60.13330.2012 "SNiP 41-01-2003 Heating, ventilation and air conditioning"
SP 73.13330.2016 "SNiP 3.05.01-85 Internal sanitary systems of buildings"
SP 75.13330.2011 "SNiP 3.05.05-84 Technological equipment and process pipelines"
SP 77.13330.2011 "SNiP 3.05.07-85 Automation Systems"
SP 131.13330.2012 "SNiP 23-01-99* Building climatology"
STO NOSTROY 2.12.69-2012 Thermal insulation works for internal pipelines of buildings and structures
STO NOSTROY 2.15.70-2011 Engineering networks of high-rise buildings. Arrangement of heat supply, heating, ventilation, air conditioning and refrigeration systems
Introduction. 2 1 area of use. 2 3. Terms and definitions, designations and abbreviations. four 4. General provisions. 5 5. Technology of work performance. eight 5.1. Technology for the manufacture of components and parts of pipelines from steel pipes. eight 5.2. Completion and preparation for the installation of sanitary equipment, heating appliances, components and parts of pipelines. ten 5.3. Mounting and assembly work. General provisions. eleven 5.4. Internal cold and hot water supply. 12 5.5. Heating and heat supply. 12 6. Testing of internal sanitary systems .. 14 6.1. General provisions for testing systems of cold and hot water supply, heating and heat supply. fourteen 6.2. Systems of internal cold and hot water supply. fifteen 6.3. Systems of heating and heat supply. fifteen 7. Starting heating systems. 16 Appendix A. Dimensions of holes and grooves for laying pipelines (air ducts) in ceilings, walls and partitions of buildings and structures. eighteen Appendix B. Form of the certificate of examination of hidden works. 19 Appendix B. Hydrostatic or Gauge Leak Test Report Form. twenty Appendix D. Form of the act of individual testing of equipment. 21 Appendix D. Form of the act of acceptance of internal systems of cold and hot water supply. 22 Annex E. Form of acceptance certificate for internal heating systems. 23 Bibliography. 24 |
Introduction
This standard was developed as part of the Standardization Program of the National Association of Builders and is aimed at implementing the "Urban Planning Code of the Russian Federation", Federal Law of December 27, 2002 No. 184-FZ "On Technical Regulation", Federal Law of December 30, 2009 No. 384- Federal Law "Technical Regulations on the Safety of Buildings and Structures", Federal Law No. 261-FZ "On Energy Saving and Improving Energy Efficiency and on Amendments to Certain Legislative Acts of the Russian Federation", Order of the Ministry of Regional Development of the Russian Federation dated December 30, 2009 No. 624 "On approval of the List of types of work on engineering surveys, on the preparation of project documentation, on construction, reconstruction, overhaul capital construction projects that affect the safety of capital construction projects.
STANDARD OF THE NATIONAL ASSOCIATION OF BUILDERS
1.1. This standard establishes the rules for the performance of work, installation, testing and commissioning of heating systems, hot and cold water supply.
2. Regulatory references
GOST 12.1.044-89 System of labor safety standards. Fire and explosion hazard of substances and materials. Nomenclature of indicators and methods for their determination
GOST 12.3.003-86 Occupational safety standards system. Electrical works. Safety requirements
GOST 8946-75 Ductile iron fittings with cylindrical thread for pipelines. Angles are passable. Main dimensions
GOST 9416-83 Building levels. Specifications
GOST 15180-86. Gaskets are flat elastic. Main parameters and dimensions
GOST 16037-80 Welded steel pipeline joints. Main types, structural elements and dimensions
GOST 17375-2001 Seamless welded pipeline parts made of carbon and low alloy steel. Elbows are steeply curved type 3D (R approx. 1.5DN). Design
GOST 19185-73 Hydraulic engineering. Basic concepts. Terms and Definitions
GOST 19431-84 Energy and electrification. Terms and Definitions
GOST 24054-80 Products of mechanical engineering and instrumentation. Leak test methods. General requirements
GOST 25136-82 Pipeline connections. Leak test methods
GOST 25151-82 Water supply. Terms and Definitions
GOST 30494-96 Residential and public buildings. Indoor microclimate parameters
GOST R 50618-93 Compensatory single-layer metal bellows. Types, general specifications
GOST R 50619-93 Compensatory multilayer metal bellows. Types, general specifications
GOST R 52948-2008 Fittings made of copper and copper alloys for connecting copper pipes by pressing. Specifications
GOST R 53484-2009 Ragged flax. Specifications
SNiP 2.04.01-85 Internal water supply and sewerage of buildings
SNiP 3.01.04-87 Acceptance for operation of completed construction projects. Key points
SNiP 3.05.01-85 Updated edition Internal sanitary systems
SNiP 12-01-2004 (SP 48.13330.2011) Organization of construction. Updated edition
SNiP 12-03-2001 Occupational safety in construction. Part 1. General requirements
SNiP 12-04-2002 Occupational safety in construction. Part 2. Construction production
SNiP 41-01-2003 Heating, ventilation and air conditioning
Note- When using this standard, check the operation of reference standards and classifiers in the public information system - on the official websites of the national body of the Russian Federation for standardization and NOSTROY on the Internet or according to annually published information indexes published as of January 1 of the current year. If the reference document is replaced (changed), then when using this standard, you should be guided by the new (changed) document. If the referenced document is canceled without replacement, the provision in which the link to it is given applies to the extent that this link is not affected.
3. Terms and definitions, designations and abbreviations
3.1. This standard uses terms in accordance with GOST 19185, GOST 25151, as well as the following terms with the corresponding definitions:
3.1.1 water heating: Type of space heating using a liquid heat carrier.
Note- Water or water-based antifreeze can be used as a coolant.
3.1.2 internal sanitary systems: Heating systems, hot and cold water supply of the building.
3.1.3. performer of works (contractor): A legal or natural person performing construction and installation work under an agreement with a customer.
3.1.4. fault: Violations in the operation of heat supply and (or) water supply systems, in which at least one of the requirements defined by the technological process is not met.
3.1.5. finished floor mark: Marking the surface of the floor, taking into account the finish of the floor covering.
3.1.6 heating: Artificial heating of premises in order to compensate for heat losses in them and maintain the temperature at a given level, determined by the conditions of thermal comfort for people in the room.
3.1.7 panel heating: A type of heating in which heat is transferred to the heated room from the heated flat surfaces of heating panels located in walls and partitions.
3.1.8 steam heating: A type of heating in which the heat carrier is steam supplied to the heating system from the heat supply network.
3.1.9 press connection: The connection of pipelines by cold mechanical deformation of the metal between the press fitting and the pipe covered by it to the depth of the socket.
3.1.10 press fitting: System element stamped in a special way for press connections of heat supply and water supply units.
Note- As an element of the system, there can be a branch, a transition, a tee, etc.
3.1.11 test pressure: Excess pressure at which a hydraulic test of the pipeline or its individual components for strength and tightness should be carried out.
3.1.12 operating pressure: The highest excess pressure that occurs during the operation of the system, without taking into account the hydrostatic pressure of the medium.
3.1.13 operating parameters of the transported medium: The maximum temperature and the highest possible water pressure in the supply pipeline, taking into account the operation of pumping stations.
3.1.14 network water: Water continuously circulating in heating networks.
3.1.15 engineering networks: Pipelines for various purposes, laid in the territories of settlements, as well as in buildings.
Note- In this standard, pipelines are understood as water supply, sewerage, heating, etc.
3.1.16 water supply system: Engineering systems buildings that consume heat for heating, ventilation and hot water supply.
3.1.17 heat supply system (ST): A set of interconnected power plants that provide heat supply to a district, city, enterprise.
[GOST 19431-84, item 26]
3.1.18 heat consumption system: A complex of heat-consuming power plants with connecting pipelines that provide heating and hot water supply in buildings and structures.
3.1.19 heating point: A set of devices intended for connection to heating networks of heating, ventilation, air conditioning, hot water supply systems for residential and public buildings.
Note- Heat points can be individual (ITP) or central (TsTP). Individual heat points are designed to connect the heat consumption systems of one building or part of it, and central - for two buildings or more.
3.1.20 coolant: Working fluid in heating systems.
3.1.21 Maintenance building: A set of works to maintain the good condition of the building, the specified parameters and modes of its operation structural elements and technical devices.
3.1.22 conditional overpressure P U, MPa: Pressure corresponding to operating conditions at normal temperature of the working medium.
3.1.23. operating organization: A legal or natural person who, on the basis of the rights of the owner or on behalf of the owner (investor), operates the constructed building.
3.2. The following designations and abbreviations are used in the standard:
D nap - outer diameter of the pipeline, mm;
P pr - overpressure, MPa;
tape FUM thread-sealing tape made of fluoroplastic sealing material.
4. General provisions
4.1. Installation of internal sanitary systems must be carried out in compliance with the requirements of SNiP 12-01-2004, SNiP 12-03-2001, SNiP 12-04-2002, instructions from equipment manufacturers, as well as this standard.
4.2. Manufacturing and installation of components and parts of heating systems and pipelines to ventilation installations with a water temperature above 388 K (115 ° C) and steam with an operating pressure of more than 0.07 MPa (0.7 kgf / cm 2) should be carried out in accordance with PB 10-573-03.
4.3. Installation of sanitary systems should be carried out with the construction readiness of buildings in the following volumes:
For industrial buildings (up to 5000 m 3) - in the volume of the entire building;
For industrial buildings (over 5000 m 3) - in the volume of a part of the building, including a separate production room, workshop, span, etc. or a set of devices (including internal drains, a heat point, a ventilation system, etc.);
For residential and public buildings up to five floors - in the volume of a separate building, one or more sections of the building;
For residential and public buildings over five floors - in the amount of five floors of one or more sections of the building.
Note- A different scheme for organizing installation is possible, depending on the accepted constructive scheme sanitary systems.
4.4. Prior to the installation of internal sanitary systems, the following work must be completed:
Installation of floors, walls and partitions on which sanitary equipment will be installed;
Construction of foundations or platforms for the installation of water heaters, pumps, heaters and other sanitary equipment;
Waterproofing device in places of installation of units of water heaters, pumps;
Laying inputs of external communications of sanitary systems into the building;
Arrangement of floors (or appropriate preparation) in places where heaters are installed on stands;
Arrangement of supports for pipelines laid in underground channels and technical undergrounds;
Preparation of holes, furrows, niches and nests in foundations, walls, partitions, ceilings and coatings necessary for laying pipelines;
Note- Dimensions of holes and grooves for laying pipelines in ceilings, walls and partitions of buildings and structures are given in Appendix A, unless other dimensions are provided for by the project. Seal openings in ceilings, walls and partitions after laying pipelines should be carried out tightly, with a fire resistance material not lower than the fire resistance of the barrier being crossed.
Application of auxiliary marks on the internal and external walls of all rooms;
Note- Places for applying auxiliary marks are determined by the design marks of the finished floor plus 500 mm.
Installation of window frames, and in residential and public buildings - installation of window sills;
Plastering (or lining) the surfaces of walls and niches in places where sanitary and heating appliances are installed, laying pipelines, as well as plastering the surface of furrows for hidden laying of pipelines in external walls;
Preparation of mounting openings in walls and ceilings for the supply of large-sized equipment;
Installation in accordance with the working documentation of embedded parts in building structures for fastening equipment and pipelines;
Ensuring the possibility of turning on power tools, as well as electric welding machines at a distance of no more than 50 m from one another;
Glazing window openings in external fences, insulation of entrances and openings in external fences.
4.5. General construction, sanitary and other special works should be carried out in sanitary facilities in the following order:
Preparation for the installation of floors, plastering of walls and ceilings, installation of beacons for the installation of ladders;
Installation of means of fastening, laying of pipelines and carrying out their hydrostatic or manometric test (see GOST 25136 and GOST 24054); waterproofing of floors;
Priming of walls, arrangement of clean floors;
Installation of bathtubs, brackets for washbasins and fittings for flushing cisterns;
First painting of walls and ceilings, tiling;
Installation of washbasins, toilet bowls and flush cisterns;
Second painting of walls and ceilings;
Installation of water fittings;
Finishing work (including sealing holes in ceilings, walls and partitions after laying pipelines);
Clean floor installation.
When installing sanitary systems and carrying out related civil works, there should be no damage to the floor, walls, ceiling, as well as structures and equipment installed in the building in the course of previous work.
4.6. Welding of steel pipes should be carried out by any method in compliance with the requirements of GOST 12.3.003.
4.6.1. Types of welded joints of steel pipelines, shape, structural dimensions of the weld must comply with the requirements of GOST 16037.
4.6.2. Welding of galvanized steel pipes should be carried out with a self-shielded wire (see GOST 2246) with a diameter of 0.8 to 1.2 mm or electrodes with a diameter of not more than 3 mm with a rutile or calcium fluoride coating, if the use of other welding materials is not provided for by the working documentation.
4.6.3. The connection of galvanized steel pipes, parts and assemblies by welding during installation should be carried out while ensuring local suction of toxic emissions or when cleaning the zinc coating for a length of 20 to 30 mm from the butt ends of the pipes, followed by coating the outer surface of the weld and the heat-affected zone with a paint containing 94% zinc dust (by weight) and 6% synthetic binders (polystyrene, chlorinated rubber, epoxy).
4.6.4. The connection of steel pipes, as well as their parts and assemblies with a nominal diameter of up to 25 mm inclusive at the construction site, should be carried out by overlap welding (see GOST 16037) (with expansion of one end of the pipe or a threadless coupling).
When welding, the threaded surfaces and the mirror surfaces of the flanges must be protected from splashes and drops of molten metal.
There should be no cracks, shells, pores, undercuts, unwelded craters, as well as burns and smudges of the deposited metal in the welded seam.
Holes in pipes with a diameter of up to 40 mm for welding nozzles must be made by drilling, milling or punching on a press.
The diameter of the hole must be equal to the inner diameter of the branch pipe with a permissible deviation of no more than 1 mm in the direction of increase.
4.7. When making a press connection, the ends of the pipes must be clean, free of scratches and grooves along the entire length, or at least along the entire length of the insert. When pipes are supplied with a synthetic coating made at the factory, the surface of the pipes must not be damaged when this coating is removed.
4.8. Installation of sanitary systems in complex, unique and experimental buildings should be carried out in accordance with the requirements of section 5 and project documentation.
4.9. When used in installation flexible hoses you should do the following:
Before installation, it is necessary to inspect the liner for the integrity of the fastening (compression) of the end fittings, the presence of a gasket, damage to the thread, braid and other defects that occurred during storage and transportation;
Install flexible hoses with a bending radius that exceeds the outer diameter by at least 5-6 times (or according to the instructions in the product passport);
Flexible hoses must not be stretched or twisted during installation and after installation;
It is not allowed to apply excessive force when tightening the tip;
Note- There is a risk of damage to the seal when tightening the tip. The tightening torque is indicated in the product data sheet.
Flexible hoses should not be exposed to open flames or excessive heat;
Every six months, it is necessary to inspect the flexible piping and check the tightness of the fastening of the end fittings;
Note- To carry out the inspection, it is necessary to provide free access to the nodes with flexible piping.
Flexible hoses should be replaced every three years;
When installing the end fittings (captive nuts) of the liner, do not use plumbing linen and other seals that can expand in a humid environment, do not allow excessive thickness of the sealing tape when installing fittings, seal the nut only with a standard sealing gasket;
It is not allowed to install the eyeliner in a tense state;
It is not allowed to operate the eyeliner at negative temperatures and near open flames;
When installing flexible hoses, give preference to flexible bellows hoses (see GOST R 50618, GOST R 50619).
5. Technology of work performance
Work on the installation of heating systems, hot and cold water supply should be carried out in accordance with GOST 30494, SNiP 3.05.01-85 Updated edition, SNiP 41-01-2003, SNiP 2.04.01-85.
5.1. Manufacturing technology of components and parts of pipelines from steel pipes
5.1.1. The manufacture of components and parts of pipelines from steel pipes should be carried out in accordance with GOST 8946, GOST 16037, GOST 25136. Manufacturing tolerances should not exceed the values \u200b\u200bspecified in table 1.
Table 1
5.1.2. The connection of steel pipes, as well as parts and assemblies from them, should be carried out by welding, on threads, union nuts and flanges (to fittings and equipment), press connections (due to cold mechanical deformation of the metal between the press fitting and the pipe covered by it to the depth of the socket ).
5.1.2.1. Galvanized pipes, assemblies and parts must be connected, as a rule, on a thread using galvanized steel connecting parts or non-galvanized ductile iron (see GOST 8946), on union nuts and flanges (see GOST 12820, GOST 12821) or on a press fittings (see GOST R 52948).
5.1.2.2. For threaded connections of steel pipes, cylindrical pipe threads in accordance with GOST 6357 (accuracy class B) should be used by knurling on light pipes and threading on ordinary and reinforced pipes.
When making a thread by knurling on a pipe, it is allowed to reduce its inner diameter by up to 10% along the entire length of the thread.
5.1.2.3. Turns of pipelines in heating and heat supply systems should be performed by bending pipes or using seamless welded carbon steel bends in accordance with GOST 17375.
Pipe bending radius:
With a nominal bore up to 40 mm inclusive, there must be at least 2.5D pipe head;
With a nominal bore of 50 mm or more, there must be at least 3.5D on the pipe.
5.1.3. In cold and hot water supply systems, pipeline turns should be performed by installing elbows in accordance with GOST 8946, pipe bends or bends. Galvanized pipes should only be bent when cold.
For pipes with a diameter of 100 mm or more, the use of bent and welded bends is allowed. The minimum radius of these bends must be at least one and a half nominal diameter of the pipe.
When bending welded pipes, the weld should be located on the outside of the pipe blank, while the plane of the weld should be at an angle of at least 45 ° to the plane of the bend.
5.1.4. Weld welding on bent sections of pipes in heating elements of heating panels is not allowed.
5.1.5. When assembling assemblies, threaded connections must be sealed. As a sealant for threaded connections at liquid temperatures in pipes up to 378 K (105 ° C), inclusive, FUM tape corresponding to TU 6-05-1388-86 or linen strand (see GOST R 53484) impregnated with red lead or white lead should be used mixed with drying oil or special sealing pastes-sealants.
As a sealant for threaded connections at a coolant temperature in pipes above 378 K (105 °C) and for condensation lines, FUM tape corresponding to TU 6-05-1388-86 or an asbestos strand together with a linen strand should be used (see GOST R 53484 ), impregnated with graphite mixed with drying oil.
FUM tape (see TU 6-05-1388-86) and linen strand (see GOST R 53484) should be applied in an even layer along the thread, preventing protrusion into and out of the pipe.
As a sealant for flange connections at a coolant temperature of not more than 423 K (150 °C), gaskets 2–3 mm thick made of paronite, or fluoroplast-4, according to GOST 15180, should be used, and at temperatures not exceeding 403 K (130 °C) gaskets made of heat-resistant rubber according to GOST 7338.
5.1.6. The flanges are connected to the pipe by welding. Deviation from perpendicularity of the flange welded to the pipe with respect to the axis of the pipe is allowed up to 1% of the outer diameter of the flange, but not more than 2 mm.
The surface of the flanges must be smooth and free of burrs. The bolt heads should be on one side of the joint.
On vertical sections of pipelines, nuts must be located from below.
The ends of the bolts must not protrude from the nuts by more than 0.5 of the bolt diameter or 3 thread pitches.
The end of the pipe, including the weld of the flange to the pipe, must not protrude beyond the mirror of the flange.
Gaskets in flange connections must not cover the bolt holes.
Installation between flanges of several or beveled gaskets is not allowed.
5.1.7. Deviations of the linear dimensions of the assembled units should not exceed ± 3 mm for a length of up to 1 m and ± 1 mm for each subsequent meter.
5.1.8. Nodes of sanitary systems must be tested for tightness at the place of their manufacture.
Assemblies of pipelines of heating systems, heat supply, internal cold and hot water supply, including those intended for embedding in heating panels, valves, taps, gate valves, mud collectors, air collectors, elevators, etc., must be subjected to hydrostatic (hydraulic), manometric or bubble (pneumatic) method in accordance with GOST 25136 and GOST 24054.
5.1.9. With the hydrostatic method of testing for tightness, air should be completely removed from the nodes, filled with water with a temperature of at least 278 K (5 ° C) and kept under excess pressure Р pr equal to 1.5 Р у.
If dew appears on the pipeline during the test, then the test should be continued after it has dried or wiped off.
5.1.10. Assemblies made of steel pipes of sanitary systems are considered to have passed the test, on the surface and at the joints of which drops, water stains will not appear and there will be no pressure drop during the test.
Valves, gate valves and cocks are considered to have passed the test if no drops of water appear on the surface and in the places of sealing devices after turning the control devices twice (before testing).
5.1.11. With the bubble method of testing for tightness, the pipeline units are filled with air with an overpressure of 0.15 MPa (1.5 kgf / cm 2), immersed in a bath of water and held for at least 30 seconds.
Assemblies are considered to have passed the test, during the test of which no air bubbles will appear in the water bath.
Tapping of connections, rotation of control devices and elimination of defects during testing are not allowed.
5.1.12. The outer surface of units and parts made of non-galvanized pipes, with the exception of threaded connections and the surface of the flange mirror, must be coated with a primer, and the threaded surface of units and parts must be coated with anti-corrosion grease, taking into account the requirements of TU 36-808-85.
5.2. Completion and preparation for the installation of sanitary equipment, heating appliances, components and parts of pipelines
5.2.1. Assemblies and parts from pipes for sanitary systems must be transported to facilities in containers or bags and have accompanying documentation.
Each container and package must be affixed with a label labeling the packed units.
5.2.2. Fittings, automation devices, instrumentation, connecting parts, fasteners, gaskets, bolts, nuts, washers, etc. not installed on parts and assemblies. must be packed separately, while the labeling of the container must indicate the designations or names of these products.
5.2.3. Water heaters, heaters, pumps, central and individual heating points, water metering units should be delivered to facilities under construction in transportable assembly-complete blocks with fasteners, piping, shut-off valves, gaskets, bolts, nuts and washers.
5.2.4. Sections of cast-iron radiators should be assembled into devices on nipples using sealing gaskets:
Made of heat-resistant rubber 1.5 mm thick at coolant temperatures up to 403 K (130 °C) according to GOST 7338;
From paronite with a thickness of 1 to 2 mm at a coolant temperature of up to 423 K (150 °C) according to GOST 15180.
5.2.5. Blocks of cast-iron radiators and finned tubes must be tested in accordance with GOST 25136 by the hydrostatic method at a pressure of 0.9 MPa (9 kgf / cm 2) or by the bubble method at a pressure of 0.1 MPa (1 kgf / cm 2). The results of bubble tests are the basis for claims for quality to manufacturers of cast-iron heaters.
Blocks steel radiators must be tested by the bubble method according to GOST 25136 with a pressure of 0.1 MPa (1 kgf / cm 2).
Convector blocks must be tested in accordance with GOST 25136 by the hydrostatic method at a pressure of 1.5 MPa (15 kgf / cm 2) or by the bubble method at a pressure of 0.15 MPa (1.5 kgf / cm 2).
After the test, the water from the heating units must be removed.
Heating panels after the hydrostatic test must be purged with air, and their connecting pipes are closed with inventory plugs.
5.3. Mounting and assembly work. General provisions
5.3.1. The connection of galvanized and non-galvanized steel pipes during installation should be carried out in accordance with 5.1.2.
Detachable connections on pipelines should be made at fittings and where necessary according to the conditions for assembling pipelines. A collapsible detachable connection at the armature should provide the possibility of replacing the armature.
Detachable connections of pipelines, as well as fittings for inspection and cleaning, should be located in places accessible for maintenance.
5.3.2. Vertical pipelines should not deviate from the vertical by more than 2 mm per 1 m of length.
5.3.3. Uninsulated pipelines of heating systems, heat supply, internal cold and hot water supply should not be adjacent to the surface of building structures.
The distance from the surface of the plaster or lining to the axis of uninsulated pipelines must be determined by the following conditions:
For nominal diameters up to 32 mm inclusive, with open laying, the distance should be from 35 to 55 mm;
For diameters from 40 to 50 mm, the distance should be from 50 to 60 mm;
For diameters greater than 50 mm, the distance should be taken according to the working documentation.
The distance from pipelines, heaters and heaters with a coolant temperature above 378 K (105 ° C) to the structures of buildings and structures made of combustible (combustible) materials in accordance with GOST 12.1.044 must be at least 100 mm.
5.3.4. Fasteners should not be located at the junctions of pipelines.
Sealing of fasteners with wooden plugs, as well as welding of pipelines to fasteners, is not allowed.
The distance between the means of fastening steel pipelines in horizontal sections is determined according to table 2, unless otherwise indicated in the project documentation.
When laying horizontal sections along traverses, the latter should be fixed on hangers on both sides of the traverse with nuts.
table 2
5.3.5. Means for fastening risers made of steel pipes in residential and public buildings are installed at a height equal to half the height of the floor of the building.
Mounting means for risers in industrial buildings should be installed at intervals of 3 m.
5.3.6. Connections to heaters with a length of more than 1500 mm must be fastened.
5.3.7. Sanitary and heating appliances must be installed plumb (see GOST 7948) and level (see GOST 9416). Sanitary cabins must be installed on a leveled base.
5.3.8. A hydrostatic test (see 5.1.9) or a pressure gauge test in accordance with GOST 25136 of pipelines with hidden laying should be carried out before they are closed with the drawing up of an inspection report for hidden work in accordance with Appendix B and SNiP 12-01-2004.
Testing of insulated pipelines should be carried out before applying insulation.
5.3.9. Heating systems, heat supply systems, internal cold and hot water supply systems, boiler room pipelines, upon completion of their installation, must be washed with water until it exits without mechanical suspensions.
5.4. Internal cold and hot water supply
5.4.1. The installation height of water fittings (distance from the horizontal axis of the fittings to sanitary appliances) should be taken:
Water folding taps and mixers from the sides of the sinks - by 250 mm, from the sides of the sinks - by 200 mm;
Toilet taps and faucets from the sides of the washbasins - by 200 mm.
5.4.2. The height of the installation of cranes from the level of the finished floor should be taken:
800 mm for taps in baths, toilet flush taps, inventory sink faucets in public and medical institutions, bath faucets;
800 mm for vidovar mixers with oblique outlet;
1000 mm for mixer taps with direct outlet;
1100 mm for faucets and oilcloth sinks in medical institutions, general faucets for bathtubs and washbasins, elbow faucets for surgical washbasins;
600 mm for taps intended for washing floors in toilet rooms in public buildings;
1200 mm for shower faucets.
5.4.3. Shower screens should be installed at a height of:
From 2100 to 2250 mm from the bottom of the grid to the level of the finished floor;
From 1700 to 1850 mm from the bottom of the grid to the level of the finished floor in cabins for the disabled;
1500 mm from the bottom of the pallet in kindergartens.
Deviations from the specified dimensions should not exceed 20 mm.
Note- For sinks with backs that have holes for taps, as well as for sinks and washbasins with countertop fittings, the installation height of the taps is determined by the design of the appliance.
5.4.4. In showers for the disabled and in preschool institutions, shower nets with a flexible hose should be used.
In rooms for the disabled, taps for cold and hot water, as well as mixers must be lever or push action.
Mixers of washbasins, sinks, as well as faucets of flushing tanks installed in rooms intended for disabled people with defects in the upper limbs, must have foot or elbow control.
5.5. Heating and heat supply
5.5.1. Slopes of piping to heaters should be made from 5 to 10 mm for the length of the piping in the direction of movement of the coolant. With a connection length of up to 500 mm, the slope of the pipes should not be performed.
5.5.2. Connection of inlets to smooth steel, cast iron and bimetallic finned pipes should be made using flanges (plugs) with eccentrically located holes to ensure free removal of air and drainage of water or condensate from the pipes. For steam connections, concentric connections are allowed.
5.5.3. Radiators of all types should be installed at distances not less than:
60 mm from the floor;
50 mm from the bottom surface of the window sills;
25 mm from the surface of the plaster walls.
Note- Distances may vary if specified by the radiator manufacturer.
In the premises of medical and preventive and children's institutions, radiators should be installed at a distance of at least 100 mm from the floor and 60 mm from the wall surface.
In the absence of a window sill, a distance of 50 mm should be taken from the top of the appliance to the bottom of the window opening.
With open laying of pipelines, the distance from the surface of the niche to the heaters should ensure the possibility of laying connections to the heaters in a straight line.
5.5.4. Convectors must be installed at a distance:
Not less than 20 mm from the surface of the walls to the fins of the convector without casing;
Close or with a gap of no more than 3 mm from the wall surface to the fins heating element wall convector with casing;
At least 20 mm from the wall surface to the casing of the floor convector.
The distance from the top of the convector to the bottom of the window sill must be at least 70% of the depth of the convector.
The distance from the floor to the bottom of a wall-mounted convector with or without a casing must be at least 70% and not more than 150% of the depth of the installed heater.
If the width of the protruding part of the window sill from the wall is more than 150 mm, the distance from its bottom to the top of convectors with a casing must be at least the height of the casing, necessary for its removal.
Connection of convectors to heating pipelines should be carried out by threading or welding.
5.5.5. Smooth and ribbed pipes should be installed at a distance of at least 200 mm from the floor and window sill to the axis of the nearest pipe and 25 mm from the wall plaster surface. The distance between the axes of adjacent pipes must be at least 200 mm.
5.5.6. When installing a heater under a window, its edge on the side of the riser, as a rule, should not go beyond the window opening. In this case, the combination of vertical axes of symmetry of heating devices and window openings is not necessary.
5.5.7. In a single-pipe heating system with one-sided open connection of heating devices, the riser to be laid should be located at a distance of 150 ± 50 mm from the edge of the window opening, the length of the connections to the heating devices should be no more than 400 mm.
5.5.8. Heaters should be installed on brackets or on stands manufactured in accordance with the working documentation or supplied complete with heaters.
The number of brackets should be set based on:
One bracket per 1 m 2 of the heating surface of a cast-iron radiator, but at least three brackets per radiator (except for radiators in two sections);
Two brackets per tube (for ribbed tubes).
Instead of upper brackets, it is allowed to install radiator strips, which should be located at 2/3 of the height of the radiator.
The brackets should be installed under the necks of the radiators; for ribbed tubes, the brackets should be installed under the pipes at the flanges.
When installing radiators on stands, the number of stands must be:
Two with up to 10 sections;
Three with more than 10 sections, while the top of the radiator must be fixed.
5.5.9. The number of fasteners per convector unit without casing should be taken as follows:
Two fastenings to a wall or to a floor at single-row and double-row installation;
Three wall mounts or two floor mounts for 3-row and 4-row installations.
For convectors supplied complete with fasteners, the number of fasteners is determined by the manufacturer.
5.5.10. Brackets for heating appliances should be fixed:
To concrete walls dowels;
To brick walls dowels or embedment of brackets with cement mortar grade not lower than 100 to a depth of at least 100 mm (excluding the thickness of the plaster layer).
The use of wooden plugs for embedding brackets is not allowed.
5.5.11. Axes of connected risers wall panels with built-in heating elements during installation must match.
The connection of the risers should be done by overlap welding (with expansion of one end of the pipe or connection with a threadless coupling).
Connection of pipelines to air heaters (heaters, heating units) must be carried out on flanges, threads, welding or bellows connection (see GOST R 50619) from flexible stainless pipes.
The suction and exhaust openings of heating units must be closed before they are put into operation.
5.5.12. Valves and check valves must be installed in such a way that the coolant flows under the valve.
Check valves must be installed horizontally or strictly vertically, depending on their design.
The direction of the arrow on the body must match the direction of the medium.
5.5.13. The spindles of double adjustment valves and control valves should be installed:
Vertically when heating devices are located without niches;
At an angle of 45 ° upwards with the location of heaters in niches.
The spindles of three-way valves must be positioned horizontally.
5.5.14. Thermometers on pipelines must be installed in sleeves, and the protruding part of the thermometer must be protected by a frame.
On pipelines with a nominal bore up to 57 mm inclusive, an expander should be provided at the place where the thermometers are installed.
Temperature sensors are mounted in accordance with the requirements and technical documentation of the manufacturer.
6. Testing of internal sanitary systems
6.1. General provisions for testing systems of cold and hot water supply, heating and heat supply
6.1.1. Upon completion of the installation work, the following must be carried out:
Testing of heating systems, heat supply, internal cold and hot water supply by hydrostatic or manometric method in accordance with GOST 25136 with drawing up an act in the form, in accordance with Appendix B, as well as flushing systems;
Individual tests of the installed equipment (see 6.2) with the preparation of an act in the form given in Appendix D;
Thermal testing of heating systems for uniform heating of heating devices.
Testing of systems using plastic pipelines should be carried out taking into account SP 40-102-2000.
Tests should be carried out before the start of finishing work.
6.1.2. During individual testing of equipment, the following work must be performed:
Checking the compliance of the installed equipment and the work performed with the design documentation;
Test equipment at idle and under load for 4 hours of continuous operation. At the same time, the balancing of the wheels and rotors in the assembly of pumps and smoke exhausters, the quality of the gland packing, the serviceability of starting devices, the degree of heating of the electric motor, and the requirements for assembly and installation of equipment specified in the technical documentation of manufacturers are checked.
6.1.3. Tests by the hydrostatic method of heating systems, heat supply and water heaters should be carried out at a positive air temperature in the premises of the building in accordance with GOST 30494.
Hydrostatic testing of cold and hot water supply systems must be carried out at an ambient temperature of at least 278 K (5 °C), while the water temperature must also be at least 278 K (5 °C).
6.2. Systems of internal cold and hot water supply
6.2.1. Internal cold and hot water supply systems must be tested by the hydrostatic or manometric method in compliance with the requirements of GOST 24054 and GOST 25136.
Hydrostatic and manometric tests of cold and hot water supply systems should be carried out before the installation of water fittings using measuring instruments in accordance with GOST 2405.
6.2.2. With the hydrostatic test method, systems are considered to have passed the test if within 10 minutes. while under pressure, no pressure drop of more than 0.05 MPa (0.5 kgf / cm 2) and drops in welds, pipes, threaded joints, fittings and water leakage through flushing devices were detected.
Upon completion of the hydrostatic test, it is necessary to release water from the internal cold and hot water supply systems.
6.2.3. Manometric tests of the internal cold and hot water supply system should be carried out in the following sequence:
Fill the system with air with an excess pressure of 0.15 MPa (1.5 kgf / cm 2), if defects in the installation are found by ear, the pressure should be reduced to atmospheric pressure and the defects should be eliminated;
Fill the system with air at a pressure of 0.1 MPa (1 kgf / cm 2), hold it under pressure for 5 minutes.
The system is recognized as having passed the test if, when it is under pressure, the pressure drop does not exceed 0.01 MPa (0.1 kgf / cm 2)
6.3. Heating and heat supply systems
6.3.1. Testing of water heating and heat supply systems should be carried out with the boilers and expansion vessels turned off by the hydrostatic method with a pressure equal to 1.5 working pressure, but not less than 0.2 MPa (2 kgf / cm 2) at the lowest point of the system.
The system is recognized as having passed the test if within 5 minutes. when it is under pressure, the pressure drop will not exceed 0.02 MPa (0.2 kgf / cm 2) and there are no leaks in welds, pipes, threaded connections, fittings, heating devices and equipment.
The pressure value in the hydrostatic test method for heating and heat supply systems connected to heating plants should not exceed the permissible overpressure value for heating appliances and heating and ventilation equipment installed in the system.
6.3.2. Gauge tests of heating and heat supply systems should be carried out in the sequence specified in 6.2.3.
6.3.3. Systems panel heating must be tested, as a rule, by the hydrostatic method.
Note- Manometric testing of panel heating systems is allowed to be carried out at negative outside temperatures.
6.3.3.1. Hydrostatic testing of panel heating systems should be carried out (before sealing the installation windows) with a pressure of 1 MPa (10 kgf / cm 2) for 15 minutes, while the pressure drop is allowed no more than 0.01 MPa (0.1 kgf / cm 2).
6.3.3.2. For surface heating systems combined with heaters, the pressure value must not exceed the allowable overpressure for heaters installed in the system.
6.3.3.3. The pressure value of panel heating systems, steam heating systems and heat supply during manometric tests should be 0.1 MPa (1 kgf / cm 2).
The duration of the test is 5 minutes.
The pressure drop should be no more than 0.01 MPa (0.1 kgf / cm 2).
6.3.4. Steam heating systems with a working pressure of up to 0.07 MPa (0.7 kgf / cm 2) must be tested by the hydrostatic method with a pressure equal to 0.25 MPa (2.5 kgf / cm 2) at the lowest point of the system.
6.3.4.1. Steam heating systems with a working pressure of more than 0.07 MPa (0.7 kgf / cm 2) must be tested by the hydrostatic method with a pressure equal to the working pressure plus 0.1 MPa (1 kgf / cm 2), but not less than 0.3 MPa ( 3 kgf/cm 2) at the top of the system.
6.3.4.2. Steam systems shall be tested in accordance with GOST 24054 and GOST 25136.
6.3.4.3. The system is recognized as having passed the pressure test if within 5 minutes. when it is under pressure, the pressure drop will not exceed 0.02 MPa (0.2 kgf / cm 2) and there are no leaks in welds, pipes, threaded connections, fittings, heating appliances.
6.3.4.4. Steam heating systems after hydrostatic or manometric tests must be checked by starting steam at the operating pressure of the system, steam leakage is not allowed.
6.3.5. Thermal testing of heating systems at a positive outdoor temperature should be carried out at a water temperature in the supply lines of the systems of at least 333 K (60 °C). In this case, all heaters should warm up evenly.
In the absence of heat sources in the warm season, a thermal test of heating systems should be carried out as the system is connected to a heat source.
6.3.6. Thermal testing of heating systems at negative outdoor temperatures should be carried out at a coolant temperature in the supply pipeline corresponding to the outdoor temperature during the test according to the heating temperature curve, but not less than 323 K (50 °C), and the circulation pressure in the system according to the project documentation .
Thermal testing of heating systems should be carried out within 7 hours, while checking the uniformity of heating of heating devices (by touch).
7. Starting heating systems
7.1. Commissioning of heating systems, hot and cold water supply must be carried out in compliance with SNiP 3.01.04-87.
Before commissioning and handing over heating, hot and cold water systems to the operating company, the contractor must check:
The state of insulation of heated buildings (sealing of leaks in window and doorways, places of passage of communications through the walls of the building, insulation of stairwells, etc.);
Serviceability of thermal insulation of the thermal unit, pipelines, fittings and equipment;
Availability and compliance with the calculation of restrictive diaphragms and balancing valves;
Availability and serviceability of instrumentation, control and safety devices;
The absence of jumpers between the supply and return pipelines of the heating unit and in the heating system or their reliable overlap;
Compliance with the working documentation for connecting the equipment of thermal units with water supply and sewerage.
7.2. The start-up of a water heating system (and/or heat supply system, ventilation and air conditioning systems, air curtains) includes:
Emptying from tap water all systems filled during flushing or pressure testing;
Filling all systems with network water or filling previously unfilled systems with water from the heating network;
Creating circulation in the system using a pump;
Adjustment of the start of the water system.
7.3. Before filling the heating system, all shut-off and control valves (with the exception of the first valves on the side of the network of the heating unit) and air valves at the upper points of the system must be opened, the first valves and drains must be closed.
7.4. Filling the heating system should be done by smoothly opening the first valve on the side of the network on the return pipeline of the heating unit. The water supply, regulated by the degree of valve opening, must ensure complete removal of air from the system. At the same time, the pressure in the return pipeline of the heating unit from the side of the network should not decrease by more than a pressure of 0.03 to 0.05 MPa (0.3 to 0.5 kgf / cm 2).
7.5. During the filling of the heating system, it is necessary to continuously monitor the air taps. Air cocks should be closed as air stops flowing out and water appears.
7.6. After filling the heating system and closing the last air cock, the valve on the supply pipeline of the heating unit should be slowly opened, which creates water circulation in the system.
7.7. If there are water metering devices (water meters) on the return pipelines, filling should be done through bypass lines, in the absence of metering devices, filling should be done through an insert installed in their place. Filling the system through a water meter is prohibited.
7.8. If the pressure in the return pipe of the heating unit is lower than the static pressure in the system, the filling of the heating system must be started via the return pipe. In the absence of a backwater (pressure) regulator on the return line of the heating unit, before filling the heating system, install a throttle diaphragm, taking into account SP 41-101-95, which will provide the necessary backwater at the estimated water flow in the system.
If there is a backwater regulator, the pipeline is covered manually.
With the smooth opening of the first valve on the side of the network on the return pipeline of the heating unit, the system is filled to the possible value determined by the pressure in the return pipeline. Further filling is carried out by smoothly opening the valve on the supply pipeline. Before performing this operation, in the absence of a backwater regulator, the valve on the return pipeline must be closed (not completely).
Slowly open the valve on the supply pipeline until the pressure in the heating system is equal to the static pressure and water flows from the highest air cock.
The indications of pressure gauges and air valves must be monitored.
Before closing the last air valve, close the valve on the supply pipeline and set the static pressure in the return pipeline using the valve or by adjusting the pressure regulator spring. When closing the last air valve, it is necessary to carefully monitor that at the moment of closing the pressure in the return pipeline does not exceed the static pressure by more than 0.05 MPa (0.5 kgf / cm 2).
7.9. After closing the air valve, the valves on the supply and return pipelines alternately open completely, and the pressure in the return pipeline must be maintained at a level exceeding the static one by 0.05 MPa (0.5 kgf / cm 2), using a regulator or a throttle diaphragm, taking into account the joint venture 41-101-95. In this case, the pressure should not exceed the allowable for this heat consumption system.
Note- When using a throttle diaphragm, it must be taken into account that with its help the set pressure in the system is ensured only at a constant water flow, for which the throttle diaphragm is designed.
7.10. After creating circulation, the air is released from the air collectors at intervals of 2 to 3 hours until it is completely removed.
7.11. After the heating system is turned on for full circulation, the pressure (pressure difference in the supply and return pipelines) and the water flow at the heating unit must be equal to the calculated values.
If a deviation of the calculated head by ± 20% or more and water flow by ± 10% or more, the causes of these deviations must be identified and eliminated.
7.12. The commissioning of heating, cold and hot water supply systems is formalized by the acts given in Annexes D and E.
Annex A
(reference)
DIMENSIONS OF HOLES AND GROOCHES FOR LAYING PIPELINES (AIR PIPELINES) IN FLOORS, WALLS AND PARTITIONS OF BUILDINGS AND STRUCTURES
Purpose of the pipeline (air duct) |
Size, mm |
||
holes |
|||
Heating |
|||
Single pipe riser |
|||
Two risers of a two-pipe system |
|||
Instrument connections and couplings |
|||
main riser |
|||
Highway |
|||
Water supply and sewerage |
|||
Plumbing stand: |
|||
One water riser and one sewer riser diameter, mm: |
|||
One sewer riser with a diameter, mm: |
|||
Two water risers and one sewer riser diameter, mm: |
|||
Three water risers and one sewer riser with a diameter, mm: |
|||
Water supply: |
|||
Sewer line, water main |
|||
sewer collector |
|||
Inputs and releases of external networks |
|||
Heat supply, not less than |
|||
Water supply and sewerage, not less than |
|||
Ventilation |
|||
Air ducts: |
|||
round section (D - duct diameter) |
|||
rectangular section (A and B - the dimensions of the sides of the duct) |
|||
Note- For openings in ceilings, the first dimension indicates the length of the opening (parallel to the wall to which the pipeline or duct is attached), the second dimension indicates the width. For wall openings, the first dimension is the width, the second is the height.
Annex B
(mandatory)
The form of the act of examination of hidden works
ACT (Name of works) performed in _____________________________________________________________ (name and location of the object) "____" ______________ 20___ Commission consisting of: representative of the construction and installation organization __________ (surname, initials, position) representative of the technical supervision of the customer ________________ (surname, initials, position) representative of the design organization (in cases of design supervision of the design organization) _____________________________________________________ (surname, initials, position) inspected the work performed by _______________________________________________ (name of construction and installation organization) and drew up this act as follows: 1. The following works were presented for examination: _______________________ (name of hidden works) 2. The work was carried out according to the design and estimate documentation ________________________ _ (name of design organization, drawing numbers and date of drawing up) 3. When performing work, _________________________________ were applied (name of materials, __________________________________________________________________________ documents confirming the quality) 4. When performing work, there are no (or allowed) deviations from design and estimate documentation _____________________________________________ (if there are deviations, indicate __________________________________________________________________________ approved by whom, drawing numbers and approval date) 5. Date: start of work _____________________________________________________________ Completion of works _______________________________________________________________ Commission decision The work was carried out in accordance with the design and estimate documentation, standards, building codes and rules and meet the requirements for their acceptance. Based on the foregoing, the production of subsequent Arrangement (installation) works _______________________________________________ (name of works and structures) Representative of the construction and installation organization _____________________ (signature) Customer Representative ______________________________ (signature) Representative of the design organization __________________________________ (signature) |
Annex B
(mandatory)
Form of act of hydrostatic or manometric leak test
ACT (system name) mounted in ________________________________________________________________ (name of the object, building, workshop) __________________________ «_____» ______________ 19__ Commission composed of representatives; customer __________________________________________________________________ __________________________________________________________________________ general contractor __________________________________________________________ ___________________________________________________________________________ installation (construction) organization ____________________________________________ (name of organization, position, initials, surname) ___________________________________________________________________________ made an inspection and quality control of the installation and drew up this act on the following: 1. Installation was carried out according to the project ______________________________________________ (name of design organization and drawing numbers) __________________________________________________________________________ 2. The test was made _________________________________________________ (hydrostatic or manometric method) pressure _____________________ MPa (____________________ kgf/cm2) within ________________________ minutes 3. The pressure drop was __________ MPa (_____________ kgf/cm2) 4. Signs of rupture or violation of the strength of the connection of boilers and water heaters, drops in welds, threaded connections, heaters, on the surface of pipes, fittings and water leakage through water fittings, flushing devices, etc. not detected (strike out the unnecessary). Commission decision: The installation was carried out in accordance with the design documentation in force. specifications, standards, building codes and rules for the production and acceptance of work. The system is recognized as having passed the pressure test for tightness. Customer Representative _____________________________ (signature) Representative of the General contractor ___________________________________________ (signature) Assembly representative (construction) organization _________________________ (signature) |
Form of the act of individual testing of equipment
ACT ___________________________________________________________________________ (name of the construction object, building, workshop) Completed in _________________________ "____" _________________ 20___ Commission composed of representatives: Customer _________________________________________________________________ (name of organization, position, initials, surname) general contractor __________________________________________________________ (name of organization, position, initials, surname) installation organization _____________________________________________________ (name of organization, position, initials, surname) have drawn up this act as follows: __________________________________________________________________________ fans, pumps, couplings, motorized self-cleaning filters, __________________________________________________________________________ control valves of ventilation systems (air conditioning) __________________________________________________________________________ (system numbers are indicated) were run-in for _____________ according to the specifications, passport. 1. As a result of the run-in of the specified equipment, it was established that the requirements for its assembly and installation, given in the documentation of manufacturers, were observed and no malfunctions were found in its operation. Customer representative __________________________________________ (signature) Representative of the General contractor _______________________________________________ (signature) Assembly representative organizations _______________________________________________ (signature) |
Form of the act of acceptance of internal systems of cold and hot water supply
We checked and accepted the internal systems of cold and hot water supply of the building for the effect of the action at _____________________________
and installed:
1. Systems are tested by hydraulic pressure at _____ atm.
(No. of acts, date)
comply with the project and SNiP 3.05.01-85
2. When testing the effect of internal water supply systems, it was found that cold and hot water flowed normally to all draw-off points.
3. The contract for the installation of apartment water meters for cold and hot water is concluded with a specialized organization _______________________________________
"____" _____________ 200_ No. _________
Based on the inspection and testing, the internal cold and hot water supply system presented for delivery is considered accepted for operation.
Form of acceptance certificate for internal heating systems
We checked and accepted the heating system for the effect of the action at:
___________________________________________________________________________
(administrative district, quarter, street, house and building number, purpose of the object)
and installed:
1. The heating system was installed in accordance with the design and regulatory and technical documentation and tested in accordance with the project and the requirement of SNiP 3.05.01-85 with hydraulic pressure at ... atm. (see act dated "___" __________).
2. The expansion vessel is installed in the central heating station (ITP) in building No. ___ in accordance with the project, isolated and provided with automatic make-up.
3. The automated control unit (ACU) (when the building is connected through the central heating station) is installed and operates in accordance with the project and regulatory and technical documentation and provides the coolant parameters corresponding to the temperature schedule and design pressures.
4. Thermostatic automatic valves for heating appliances are installed in accordance with the project and have temporary protective caps or thermoelements (heads). In case of non-installation of thermoelements (heads) for the period of acceptance of the heating system, an agreement was presented with a specialized organization No. ___ dated __________ on acceptance for storage and subsequent installation of thermoelements.
(heads)
5. In a two-pipe heating system on thermostatic valves, the valves were adjusted to the positions corresponding to the design values for each room.
6. If there are balance valves on the sectional nodes and risers of the heating system, the installation adjustment of the valves was carried out to the positions corresponding to the design values for each riser.
7. Checking the effect of the entire heating system as a whole (with installed thermostatic elements) showed that at the outside air temperature Tn = _______ deg. C, supply water temperature at control units Tk = _____ deg. C, return water temperature To = _____ deg. C, circulation pressure _____ m, while all devices of the heating system had uniform heating. The temperature in the interior was _______ degrees. FROM.
Based on the inspection and testing performed, the heating system presented for delivery is considered accepted for operation.
Bibliography
Urban Planning Code of the Russian Federation |
||
Federal Law of December 30, 2009 No. 384-FZ "Technical Regulations on the Safety of Buildings and Structures" |
||
Federal Law No. 261-FZ “On Energy Saving and Improving Energy Efficiency and on Amendments to Certain Legislative Acts of the Russian Federation” |
||
Order of the Ministry of Regional Development of the Russian Federation dated December 30, 2009 No. 624 "On approval of the List of types of work on engineering surveys, preparation of project documentation, construction, reconstruction, overhaul of capital construction facilities that affect the safety of capital construction facilities" |
||
Device rules and safe operation steam and hot water pipelines. Approved by the resolution of Gosgortekhnadzor |
||
TU 6-05-1388-86 |
FUM thread sealing tape |
|
Enlarged mounting units made of steel pipes for internal plumbing, hot water and heating systems |
||
SP 40-102-2000 |
Design and installation of pipelines for water supply and sewerage systems using polymeric materials |
1 area of use
2 Normative references
3 Terms and definitions, designations and abbreviations
4 General provisions
5 Pressure pipes
5.1 Requirements for pressure tubing
5.2 Pressure pipes
5.2.1 Pressure steel pipes
5.2.1.1 Fittings for steel pipes
5.2.1.2 Connections for steel pipes
5.2.2 Pressure copper pipes
5.2.2.1 Connections for copper pipes
5.2.2.2 Connections for copper pipes
5.2.3 Metal-polymer pressure pipes
5.2.3.1 Connection parts for multilayer pipes
5.2.3.2 Joints for multilayer pipes
5.2.4 Polypropylene pressure pipes
5.2.4.1 Fittings for polypropylene pipes
5.2.4.2 Connections for polypropylene pipes
5.2.5 XLPE pressure pipes
5.2.5.1 Fittings for XLPE pipes
5.2.5.2 Connections for XLPE pipes
5.2.6 Chlorinated PVC pressure pipes
5.2.6.1 Connections for chlorinated PVC pipes
5.2.6.2 Chlorinated PVC pipe fittings
5.2.7 Polybutene pressure pipes
5.2.7.1 Fittings for polybutene pipes
5.2.7.2 Connections for polybutene pipes
5.2.8 Acrylonitrile butadiene styrene pressure pipes
5.2.8.1 Fittings for acrylonitrile butadiene styrene pipes
5.2.8.2 Connections for acrylonitrile butadiene styrene pipes
5.3 Technological features of the connection of pressure polymer pipes
5.3.1 Types of connections for pressure plastic pipes
5.3.2 Welding of polyolefin pressure tubing
5.3.3 Pressure tubing connections made of unplasticized PVC, chlorinated PVC and acrylonitrile butadiene styrene
5.3.4 Welding of polypropylene pressure tubing
5.4 Fastening pressure pipes
6 Sewer pipes
6.1 Requirements for sewer pipes
6.2 Sewer pipes
6.2.1 Gray cast iron sewer pipes
6.2.1.1 Connection parts for gray cast iron sewer pipes
6.2.1.2 Gray cast iron sewer pipe connections
6.2.2 Ductile iron sewer pipes
6.2.2.1 Ductile iron sewer fittings
6.2.2.2 Ductile iron sewer pipe connections
6.2.3 Unplasticized PVC sewer pipes
6.2.3.1 Connections for unplasticized PVC sewer pipes
6.2.3.2 Connections for unplasticized PVC sewer pipes
6.2.4 Thick-walled PVC sewer pipes
6.2.4.1 Connections for heavy-wall PVC sewer pipes
6.2.4.2 Connections for heavy-wall PVC sewer pipes
6.2.5 Sewer pipes made of polyethylene
6.2.5.1 Connections for polyethylene sewer pipes
6.2.5.2 Connections for polyethylene sewer pipes
6.2.6 Sewer pipes made of filled polyethylene
6.2.6.1 Connections for sewer pipes made of filled polyethylene
6.2.6.2 Connections for sewer pipes made of filled polyethylene
6.2.7 Polypropylene sewer pipes
6.2.7.1 Connection parts for polypropylene sewer pipes
6.2.7.2 Connections for socket sewer pipes made of polypropylene
6.2.8 Sewer pipes made of filled polypropylene
6.2.8.1 Connections for sewer pipes made of filled polypropylene
6.2.8.2 Connections for sewer pipes made of filled polypropylene
6.2.9 Connections for assembling different sewer pipes
6.3 Fasteners for gravity pipelines
7 Pipe procurement
7.1 Bending pipes for pressure and sewer pipes
7.2 Manufacture of blanks from pressure pipes for water pipes
7.3 Production of connections from pressure polyethylene pipes for water pipes
7.4 Manufacture of blanks for internal fire water pipelines
7.5 Production of water seals for internal drains
7.6 Manufacture of units from polymer sewer pipes
7.7 Completion of shaft packages with pressure water and sewer pipe blanks
7.8 Acquisition of sanitary cabins with pressure water and sewer pipe blanks
7.9 Making bays-risers for internal drains
8 Installation of internal water pipes
8.1 Typical structures of technological processes for the installation of internal water pipes
8.2 Technical documentation for installation and assembly work
8.3 Organization of work on the installation of internal water pipes
8.4 Preparatory work
8.5 Ancillary work
8.6 Assembly of internal plumbing
9 Installation of sewer pipelines
9.1 Typical structures of technological processes for the installation of internal sewerage
9.2 Requirements for the project of internal sewerage
9.3 Requirements for the installation project of internal sewerage
9.4 Assembling the internal sewerage system
9.5 Quality control of the assembly of sewer pipelines
10 Installation of internal drains
10.1 Arrangement of internal drainage systems
10.2 Typical structures of technological processes for the installation of internal gutters
10.3 Production of installation work on the assembly of internal gutters
10.4 Quality control of the assembly of internal gutters
11 Testing of internal piping systems
11.1 Testing cold and hot water pipes
11.2 Testing fire-fighting water pipes
11.3 Testing sewer pipes
11.4 Testing of internal drains
12 Handover and acceptance of internal pipelines
12.1 General
12.2 Delivery and acceptance of internal water pipes
12.3 Delivery and acceptance of internal sewerage
12.4 Delivery and acceptance of internal drains
13 Safety, fire safety and environmental safety when installing internal piping systems
Annex A (informative). Symbols of sewer pipe products
Appendix B (recommended). The form of the certificate of examination of hidden works on internal water supply and sanitation systems
Annex B (recommended). The form of the act based on the results of tests of cold / hot water supply
Appendix D (recommended). The form of the act based on the results of tests of the internal sewerage system
Annex D (recommended). The form of the act based on the results of tests of the internal drainage system
Annex E (recommended). A sample of the act of testing the internal fire-fighting water supply for performance
Appendix G (recommended). Sample test report for internal fire water supply for water loss
Annex I (recommended). Sample test report for fire hydrants for serviceability
Annex K (recommended). Sample certificate of acceptance of internal fire-fighting and utility and hot water pipes
Annex L (recommended). Sample act of acceptance of internal sewerage
Annex M (recommended). Sample act of acceptance of internal drains
Bibliography